Concrete Yards Calculator

Concrete

Quick answer: ready-mix concrete is sold by the cubic yard, and this calculator turns your slab, footing or column dimensions into yards — including a waste allowance and an estimated delivery cost. A 10×10 ft slab at 4 inches thick needs 1.36 cubic yards with 10% waste, about $204 at $150 per yard before delivery fees.

–
Cubic yards to order
–
Cubic feet
–
Cubic metres
–
Equal to 80 lb bags
–
Estimated concrete cost

Yards include your waste allowance. Cost is concrete only — most plants add a delivery fee, and orders under about 3 yards often carry a short-load fee.

How it works — the formula

Every ready-mix estimate is a volume problem. For a slab or footing:

Volume (ft³) = Length (ft) × Width (ft) × Thickness (in) ÷ 12

For a round column or pier:

Volume (ft³) = π × (Diameter (in) ÷ 24)² × Depth (ft) × Number of columns Cubic yards = ft³ × (1 + waste %) ÷ 27  ·  Estimated cost = Cubic yards × Price per yard

One cubic yard is 27 cubic feet (0.76 m³). Ready-mix is usually sold in quarter-yard or half-yard steps, so round your order up to the nearest step your plant offers — and order the waste allowance, because a truck that runs short costs far more in a second delivery fee than the extra quarter yard.

Worked examples

ProjectVolume (with waste)Yards to orderEst. cost at $150/yd³
Patio slab 10 × 10 ft, 4 in thick, 10% waste36.7 ft³1.36 yd³$204
Driveway slab 20 × 12 ft, 6 in thick, no waste120 ft³4.44 yd³$667
4 deck piers, 12 in Ø × 4 ft deep, 10% waste13.8 ft³0.51 yd³$77

Check the first row by hand: 10 × 10 × (4 ÷ 12) = 33.3 ft³. Add 10% → 36.7 ft³. Divide by 27 → 1.36 yd³. Small job? Below about 1 yard, bags usually win — see the Concrete Bag Calculator for bag counts.

Frequently asked questions

How many cubic yards of concrete do I need for a 10x10 slab?

A 10×10 ft slab at 4 in thick is 33.3 ft³ = 1.23 yd³ exactly, or 1.36 yd³ with 10% waste. At 6 in thick: 1.85 yd³, or 2.04 with waste.

How do I convert cubic feet to cubic yards?

Divide by 27 — a cubic yard is a 3 ft cube, 3 × 3 × 3 = 27 ft³.

How much waste should I add to a ready-mix order?

5–10%. Uneven subgrade, spillage and formwork movement all eat concrete; running short mid-pour is the expensive outcome.

What does a cubic yard of ready-mix cost?

Roughly $130–$180 per yard for standard mixes in the US in 2026, plus delivery and any short-load fee. Enter your plant's quote above for a local estimate.

How many 80 lb bags equal one cubic yard?

45 bags — each 80 lb bag yields about 0.60 ft³, and 27 ÷ 0.60 = 45.

Related tools

Concrete Bag Calculator Concrete

The same volume as 40/60/80 lb bag counts — better for pours under a yard.

Open the calculator →
Gravel Calculator Bases & masonry

Cubic yards and tons for the base layer under your slab.

Open the calculator →
Paver Calculator Yard & patio

Pavers, base gravel and bedding sand for patios and paths.

Open the calculator →
Sand Calculator Bases & play

Tons and bags of sand for bases, sandboxes and pools.

Open the calculator →

See the full list on the Home & DIY Calculators page.

Estimates only. This calculator gives planning volumes for typical residential pours; it is not a structural or engineering calculation. Confirm the order quantity, mix design and delivery terms with your ready-mix plant before pouring.